Analisis efektifitas penerapan Critical Path Method (CPM) pada proyek pembangunan tanggul Kali Lamong Kabupaten Gresik

Authors

  • Andrian Firdaus Yusuf Al Qordhowi Universitas Sunan Giri Surabaya Sidoarjo
  • Rafi Fendrawan Universitas Sunan Giri Surabaya

DOI:

https://doi.org/10.31004/jutin.v8i1.36105

Keywords:

Time and Cost Management, Critical Path method, Microsoft Project 2019

Abstract

On construction projects, time and cost are very important and are one measure of success, along with budget and quality. Schedule the project to complete it quickly and efficiently. Critical Path Method (CPM) is a project planning and control method used to identify the most critical or crucial sequence of activities in a project. By determining the critical path, the project manager can know which activities have a very limited time tolerance so that they cannot be delayed without affecting the overall project schedule. The results of the analysis of the Microsoft Project 2019 application show that there are 13 critical work units. After analyzing the acceleration of duration using the method of additional overtime working hours and rescheduling using Microsoft Project 2019, the time comparison was found as follows: Work duration for the original Lamong River embankment construction item 295 days increased to 245 working days after the additional hours (crashing) with a total cost of Rp. 15,137,716,928.72 The percentage of time efficiency after the crashing was 16.95% with a duration difference of 50 working days. The cost efficiency percentage after accelerating with additional hours is 0.05% with a cost difference of Rp. 775,106,996.72.

References

Aulia, M. Zikril. Penerapan Metode CPM (critical path method) Pada Proyek Konstruksi Pembangunan Bendungan LauSimeme Paket II Kab. Deli Serdang. Diss. UMSU, 2021.

Aulia, Syfa Safitri. "Analisis Penjadwalan Proyek Gedung Menggunakan Metode CPM-PERT (Critical Path Method-Program Evaluation And Review Technique)(Studi Kasus Proyek Pembangunan Gedung APSLC Universitas Gadjah Mada)." (2021).

Sihotang, Lisa Handayani. Evaluasi Pengendalian Waktu dan Biaya pada Proyek Peningkatan Ruas Jalan Nasreuhe-Lewak-Sibigo Kab. Simeulue dengan Metode CPM Dan PERT. Diss. 2021.

Irawan, Dede, et al. "Model Analisis Pelaksanaan Proyek dengan Metode Critical Path Method (CPM) dan Metode Crashing (Study Kasus pada Pelaksanaan Pekerjaan Peningkatan Jalan Kebandingan–Gembongdadi, Kecamatan Kramat, Kabupaten Tegal)." Infratech Building Journal 1.02 (2020): 96-102.

Hutasoit, P. hubertus, B.F.Sompie, & Pratasis, P. A. K. (2014). PENGARUH PERCEPATAN DURASI TERHADAP PENINGKATAN BIAYA. (STUDI KASUS : PERUMAHAN PURI KELAPA GADING). TEKNO SIPIL, 12(61), 54–64.

Ningrum, Fika Giri Aspia. "Penerapan Metode Crashing Dalam Percepatan Durasi Proyek Dengan Alternatif Penambahan Jam Lembur dan Shift Kerja." (2016).

Astutik, Fuji. "Pengoptimalisasi Pelaksanaan Proyek Pembangunan Gedung Pasca Sarjana IAIN Tulungagung dengan Penggunaan Metode CPM." Skripsi. Fakultas ekonomi. Universitas Nusantara PGRI Kediri (2015).

Nalhadi, Ahmad, and Nana Suntana. "Analisa Infrastruktur Desa Sukaci-Baros Dengan Metode Critical Path Method (CPM)." Jurnal Sistem dan Manajemen Industri 1.1 (2017): 35-42.

Abas, Nazilah P., et al. "Analisa Waktu Pelaksanaan dan Biaya Menggunakan Metode CPM dan Metode Crashing Pada Proyek Pembangunan Laboratorium Forensik Polda Sulut." Jurnal Produk Terapan Unggulan Vokasi 1.1 (2022): 1-12.

Ahsan, Hafi, Lila Ayu Ratna Winanda, and Maranatha Wijayaningtyas. "ANALISIS PENJADWALAN DENGAN METODE CRASHING." STUDENT JOURNAL GELAGAR 4.2 (2022): 217-224.

Downloads

Published

2025-01-17

How to Cite

Qordhowi, A. F. Y. A., & Fendrawan, R. (2025). Analisis efektifitas penerapan Critical Path Method (CPM) pada proyek pembangunan tanggul Kali Lamong Kabupaten Gresik. Jurnal Teknik Industri Terintegrasi (JUTIN), 8(1), 769–776. https://doi.org/10.31004/jutin.v8i1.36105