Optimasi Biaya dan Waktu Dengan Metode TCTO pada Pembangunan Casting Mechanical & Civil Work For Oil Storage And Steady Room Workshop Gresik

Authors

  • Alia Maharani Endriastuti Universitas 17 Agustus 1945 Surabaya
  • Masca Indra Triana Universitas 17 Agustus 1945 Surabaya, Indonesia

DOI:

https://doi.org/10.31004/jutin.v7i2.28837

Keywords:

Optimal; Metode TCTO; Percepatan; Lembur; Kompresi

Abstract

In planning a project in addition to time and resource variables, cost variables (costs) have a very important role. This research was conducted on the construction of Casting Mechanical &; Civil Work For Oil Storage And Steady Room Workshop Gresik. The purpose of this study is to obtain more efficient optimal cost and time using the Time Cost Trade Off (TCTO) method. This research is carried out by means of compression or emphasis on activities that are on a critical task. From the results of the analysis with the alternative of crashing the addition of working hours (overtime), it was found that the duration of the crashing results for 1 hour of overtime was 175 days, 2 hours of overtime 173 days, and 3 hours of overtime 172 days. As for the crash cost, 1 hour of overtime is Rp. 3,123,406,448 while 2 hours is Rp. 3,119,117,964 and 3 hours of overtime is Rp. 3,117,248,350. Of the three durations, it produces an optimal time of 172 working days with a time efficiency of 3.37% and an optimal cost of Rp. 3,117,248,350 with a cost efficiency of 0.42% with an overtime duration of 3 hours.

References

Florensia, A. M. (2016). Analisis Time Cost Trade Off untuk Mengejar Keterlambatan Proyek. Jurnal Ilmiah Teknik Sipil.

Ikhtisholiyah. (2017). Analisis Penerapan Manajemen Waktu dan Biaya Pada Proyek Pembangunan Gedung Kuliah Teknik Listrik Industri Politeknik Negeri Madura (POLTERA). Zeta - Math Journal Volume 3 No. 01, 14-21.

Nurdiana, A. (2015). Analisis Biaya Tidak Langsung Pada Proyek Pembangunan Best Western Star Hotel & Star Apartement Semarang. TEKNIK, 105-109.

Simatupang, J. S., Dundu, A. K., & Sibi, M. (2015). Pengaruh Percepatan Durasi Terhadap Waktu Pada Proyek Konstruksi (Studi Kasus: Pembangunan Persekolahan Eben Haezar Manado). Jurnal Sipil Statik Vol.3 No.5, 281-291.

Janizar, S., Rahman, T., & Schipper, L. A. (2023). Kajian Percepatan Proyek Menggunakan Metode Time Cost Trade Off Dengan System Penambahan Pekerja (Studi Kasus : Pembangunan Gedung RS Jantung Paramarta Bandung). Jurnal Teknik Sipil Cendekia, 685-704

Hendriyani, I., Pratiwi, R., & Qadri, N. (2020). Optimasi Waktu dan Biaya Pada Pelaksanaan Proyek Peningkatan Jalan Bina Bakti Kelurahan Gunung Seteleng Kabupaten Penajam Paser Utara Dengan Metode Time Cost Trade Off (TCTO). Jurnal TRANSUKMA Volume 03 Nomor 01, 65-76.

Downloads

Published

2024-04-22

How to Cite

Endriastuti, A. M. ., & Triana, M. I. . (2024). Optimasi Biaya dan Waktu Dengan Metode TCTO pada Pembangunan Casting Mechanical & Civil Work For Oil Storage And Steady Room Workshop Gresik. Jurnal Teknik Industri Terintegrasi (JUTIN), 7(2), 1037–1048. https://doi.org/10.31004/jutin.v7i2.28837