Earned Value Analysis Terhadap Biaya dan Waktu pada Proyek Pembangunan Gudang Produksi PP. Indopack Printing Nganjuk
DOI:
https://doi.org/10.31004/jutin.v7i3.31047Keywords:
Cost Performance, Time, Earned Value Analysis, Estimated Project CompletionAbstract
Earned Value Analysis is a technique of analyzing cost and time to obtain the performance achieved per time on a project, so that users are able to predict the cost and time required to complete the remaining project work. The prediction is calculated with the assumption that the performance of completing the rest of the project will be the same and constant as the performance obtained when the review was conducted. Thus, a system is needed to integrate cost and time information. The Earned Value concept is an analysis used in project management by integrating cost and time. The results show the value of Cost Variance (CV) week 16 during the review of Rp.1,995,516,896, Schedule Variance (SV) of Rp.-162,490,873 which shows there is no cost overrun in implementation but the schedule is not according to plan. While the Schedule Performance Index (SPI) value of 0.994 < 1 and Cost Performance Index (CPI) of 1.070 means that the project is delayed but still profitable. The results of the analysis of the costs required to complete the remaining project Estimate To Complate (ETC) at week 16 review with a value of Rp. 19,270,138,044. While the results of the analysis of the amount of time required to complete the Estimate To Schedule (ETS) project amounted to 126.76 with a rounding of 127 days.References
Abrar, Husen. 2011. Manajemen Proyek : Perencanaan, Penjadwalan, dan Pengendalian Proyek. Yogyakarta : Andi.
Amaliyah, Rizky. 2016. Pengendalian progress waktu dan biaya dengan metode Earned Value pada proyek pembangunan Gedung Pusat Riset tahap 1 Kampus ITS Sukolilo Surabaya.
Aquilano, Nocholas J. Jacobs, F. Robert, Chase, Richard B. 2007. Operations Management for Competitive Advantage, 7thedition, Mc Graw Hill, New York.
Asiyanto, 2005. Construction Project Cost Management, edisi dua, Penerbit Pradnya Paramita, Jakarta.
Assaf et al. 1995. Causes of Delay in Large Building Contruction Project.
Dimyati. H. dan Nurjaman, K. 2014, Manajemen Proyek, Cetakan Pertama, Pustaka Setia, Bandung.
Dipohusodo, Istimawan. 1996. Manajemen Proyek dan Konstruksi, Jilid I, Edisi Pertama, Penerbit Kanisius, Yogyakarta.
Djojowirono, S. 1984. Manajemen Konstruksi. Yogyakarta : Biro penerbit KMTS Fakultas Teknik UGM.
Ervianto, Wulfram I. 2002. Manajemen Proyek Konstruksi, Edisi Pertama, Salemba Empat, Yogyakarta.
Ervianto, Wulfram I. 2005. Manajemen Proyek Konstruksi, Edisi Revisi, Andi : Yogyakarta.
Gunawan, Sahrul. 16 Juni 2016. “Makalah Critical Path Method (CPM)”. Di http://sahrulgunawancunklie.blogspot.com/ diakses pada tanggal 14 September 2018.
Heizer, J. dan Render, B. 2006. Manajemen Operasi, Edisi 7. Jakarta : Salemba Empat.
Messah, Yunita A., Lona, Lazry Hellen P., dan Sina, Dantje A.T. 2013. Pengendalian Waktu Dan Biaya Pekerjaan Konstruksi Sebagai Dampak dari Perubahan Desain (Studi Kasus Embung Oenaem, Kecamatan Biboki Selatan, Kabupaten Timor Tengah Utara). Tugas Akhir, Jurusan Teknik Sipil Universitas Nusa Cendana, Kupang.
Izeul Maromi, Muhammad dan Indryani, Retno. 2015 Earned Value untuk analisa kinerja biaya dan waktu pelaksanaan pada proyek pembangunan Condotel De Vasa Surabaya
Pamungkas, Agung., Sugiarto., dan Setiono. 2013. Analisis Nilai hasil terhadap waktu dan biaya pada proyek konstruksi (Studi Kasus Proyek ICB Civil Work Construction off Spillway of Countermeasures in Wonogiri). Tugas Akhir Jurusan Teknik Sipil Universitas Sebelas Maret, Surakarta
Meredith. J. 2000, Project Management, A Managerial Approach. John Wiley and Sons, inc. New York.
Monica. 2013. Praktek Perencanaan Dan Pengendalian Biaya Proyek Pada Kontraktor Di Nunukan Kalimantan Timur. Tesis. Universitas Atma Jaya Yogyakarta. Yogyakarta.
Nugraha. A, 2022, Metode Nilai Hasil (Earned Value Method), URL : https://www.slideshare.net/ AnggaNugraha15/pengendalian - proyek dengan - metode – nilai – hasil – earned – value - method.
Pahalawan. F.A. 2015. Analisis Konsep Nilai Hasil (Earned Value Analysis) Terhadap Waktu Dan Biaya Pada Pekerjaan Proyek Pembangunan Gedung.Skripsi. Universitas Jember. Jember.
Soeharto I. 1997, Manajemen Proyek jilid2.Erlangga. Jakarta.
Soeharto I., 1995, Manajemen Proyek Dari Konseptual Sampai Operasional.Erlangga. Jakarta.
Widiasanti, I. dan Lenggogeni. 2013, Manajemen Konstruksi. PT. Remaja Rosdakarya Offset. Bandung.
Wulfram. 2004, Teori Aplikasi Manajemen Proyek Konstruksi. CV. Andi Offset.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2024 Dimas Gusti Wiranegara, Gede Sarya, Masca Indra Triana
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.