Evaluasi Waktu dan Biaya Proyek Menggunakan Metode Crashing melalui Penambahan Jam Kerja pada Proyek Pembangunan Gedung Diagnostik Terpadu RSUD Sidoarjo

Authors

  • M Alfariz Akbar Aziz Universitas 17 Agustus 1945 Surabaya
  • Masca Indra Triana Universitas 17 Agustus 1945
  • Mochammad Firmansyah Universitas 17 Agustus 1945

DOI:

https://doi.org/10.31004/jutin.v8i4.51443

Keywords:

Project Optimization, Crashing Method, Working Hours Extension, Cost Evaluation, Time Acceleration

Abstract

This study aims to evaluate the project’s time and cost using the crashing method This study was conducted to evaluate the time and cost performance of a project using the crashing method by extending daily working hours in the Integrated Diagnostic Building Construction Project at RSUD Sidoarjo. The main purpose of this research is to determine the most efficient combination of project duration and cost while calculating the additional expenses resulting from the application of the crashing method. The data were obtained from project schedules, progress reports, and detailed cost breakdowns for each activity. The analysis began by calculating the normal project duration, then comparing it to the results after applying the crashing method through additional working hours of 1, 2, and 3 hours per day. The results show that the original project duration of 200 days can be shortened to 199 days with an extra hour, to 198 days with two additional hours, and to 197 days with three additional hours per day. The total project costs after crashing were IDR 45,320,447,319.55 for one-hour addition, IDR 45,286,606,288.69 for two-hour addition, and IDR 45,252,907,565.9 for three-hour addition.

References

Armalisa, A., Fauzi, R., & Yulinda, E. (2020). Analisis percepatan waktu proyek menggunakan metode crashing (studi kasus proyek pembangunan gedung). Jurnal Teknik Sipil dan Teknologi Konstruksi, 6(1), 45–53.

Ervianto, W. I. (2004). Teori—Aplikasi Manajemen Proyek Konstruksi. Yogyakarta: Andi Offset.

Kerzner, H. (1998). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (6th ed.). New York: John Wiley & Sons.

Manik, I. P. M., & Ardana, P. D. H. (2023). Analisis percepatan durasi proyek dengan metode crashing pada proyek konstruksi. Jurnal Teknik Sipil, 12(2), 101–110.

Massie, M. (2022). Perencanaan dan pengendalian waktu serta biaya proyek konstruksi menggunakan CPM. Jurnal Rekayasa Sipil, 9(3), 221–230.

Soeharto, I. (1999). Manajemen Proyek: Dari Konseptual sampai Operasional (Edisi Revisi). Jakarta: Erlangga.

Widhiarto, H., & Nugroho, S. (2014). Analisis efisiensi waktu dan biaya proyek menggunakan metode crashing. Jurnal Konstruksi, 2(1), 34–42.

Downloads

Published

2025-10-20

How to Cite

Aziz, M. A. A., Triana, M. I., & Firmansyah, M. (2025). Evaluasi Waktu dan Biaya Proyek Menggunakan Metode Crashing melalui Penambahan Jam Kerja pada Proyek Pembangunan Gedung Diagnostik Terpadu RSUD Sidoarjo. Jurnal Teknik Industri Terintegrasi (JUTIN), 8(4), 4480–4485. https://doi.org/10.31004/jutin.v8i4.51443

Issue

Section

Articles of Research

Similar Articles

<< < 12 13 14 15 16 17 18 19 20 21 > >> 

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)