Produktivitas Pekerja pada Pekerjaan Pembesian Balok pada Pembangunan Gedung Kantor PX. X di Surabaya

Authors

  • Ariansyah Malik Universitas 17 Agustus 1945 Surabaya
  • Michella Beatrix Universitas 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.31004/jutin.v8i3.44469

Keywords:

Construction management, Productivity; Labor, Labor utilization rate, Productivity rating

Abstract

Successful construction management can be seen from the achievement in managing construction projects that are completed on time as planned. In this research project does not calculate worker productivity, there is no target for each work item, only the final target of the project and this project does not have calculations related to labor productivity, which results in an impact on the achievement of work targets. Therefore, researchers conducted research with the aim of knowing the productivity value of labor. This research was conducted at the office and house building construction project of PT X located at Jl. Komering, Darmo, Wonokromo sub-district, Surabaya. The result of the research is the value of labor productivity on the construction project of the office building and the house of PT X is classified as an effective or satisfactory category, obtained the average value of LUR on beam concreting work of 81.52% morning time and 76.33% afternoon time.

References

Afnaldi, A., Masril, & Dewi, S. (2022). Perencanaan Struktur Atas Pembangunan Kantor Camat Kecamatan Kinali Pasaman Barat Provinsi Sumatera Barat. Ensiklopedia Research And Community Service Review, 1(2). Http://Jurnal.Ensiklopediaku.Org

Allam, R., Pratama, Z., & Nugraheni, F. (2020). Analisis Produktivitas Tenaga Kerja Di Lapangan Pada Pekerjaan Kolom.

Alvin, T., & Waty, D. M. (2020). Faktor-Faktor Yang Mempengaruhi Produktivitas Tenaga Kerja Pada Bangunan High Rise Di Republik Indonesia. Dalam Jmts: Jurnal Mitra Teknik Sipil (Vol. 3, Nomor 4).

Ambarwati Wijaya, G., Ketut Sucita, I., Saputra, J., GA-Siwabessy, J. D., & Beji, K. (2021). Analisis Tingkat Dan Faktor Produktivitas Tenaga Kerja Pada Pekerjaan Struktur Atas Di Proyek X. Dalam Jurnal Teknik Sipil (Vol. 13, Nomor 2).

Diana, V. S., & Beatrix, M. (2022). Perbandingan Produktivitas Pekerja Di Lapangan Dengan Permen PUPR 2022 Pada Proyek Guest House Exindo 57 Kabupaten Nganjuk. Jurnal Extrapolasi, 19.

Fassa, F., Soekiman, A., & Wibowo, A. (2021). Manajemen Risiko Di Industri Konstruksi Periode 2017 S.D 2020: Tinjauan Sistematis Dan Analisis Konten.

Fatkhul Adzim, M., & Beatrix, M. (2023). Analisis Nilai Labour Utilitation Rate Tenaga Kerja Pada Pekerjaan Struktur Beton.

Firda, A., Hanafiah, & Akhirini. (2023). Produktivitas Pekerja Dengan Menggunakan Metode Work Sampling (Pekerjaan Pemasangan Tiang Pancang). Dalam Jurnal Lateral (Vol. 1, Nomor 1).

Iroth, V. G., Malingkas, G. Y., & Tjakra, J. (2024). Produktivitas Tenaga Kerja Pada Pekerjaan Dinding Dengan Menggunakan Metode Work Sampling Pada Proyek Pembangunan Ruko Cluster Amethyst Kawanua Emerald City Manado. In Tahun (Vol. 22, Issue 87).

Norjana, N., & Zulfiati, R. (2020). Analisa Produktivitas Tenaga Kerja Terhadap Pekerjaan Kolom Dan Balok Beton Bertulang. Jurnal Talenta Sipil, 3(2), 82. Https://Doi.Org/10.33087/Talentasipil.V3i2.33

Downloads

Published

2025-07-04

How to Cite

Malik, A., & Beatrix, M. (2025). Produktivitas Pekerja pada Pekerjaan Pembesian Balok pada Pembangunan Gedung Kantor PX. X di Surabaya. Jurnal Teknik Industri Terintegrasi (JUTIN), 8(3), 2300–2305. https://doi.org/10.31004/jutin.v8i3.44469