Analisis Optimalisasi Waktu dan Biaya dengan Penambahan Jam Metode Time Cost Trade Off

Authors

  • Muhammad Oka Mahendra Universitas Serang Raya
  • Teguh Eko Saputro Universitas Serang Raya
  • Al Fiillian Sah Putra Universitas Serang Raya

DOI:

https://doi.org/10.31004/jutin.v8i2.44078

Keywords:

Crashing, Critical Path Method, Jam Lembur, Optimalisasi, Time Cost Trade Off

Abstract

Construction projects are bound by predefined schedules and budgets established from the outset. This study aims to optimize time and cost through a 3-hour daily overtime intervention, focusing on evaluating schedule acceleration effectiveness and resource efficiency. The Time Cost Trade Off (TCTO) method was applied via crashing techniques, systematically calculating cost-time trade-offs. Analysis centered on critical paths identified using the Critical Path Method (CPM), with schedule compression achieved through additional work hours. The findings reveal that the project duration was reduced from 180 days to 145 days, achieving a 35-day reduction (19.4%). This outcome demonstrates that targeted overtime interventions on critical activities optimize time allocation without compromising cost control, while affirming the relevance of the TCTO-CPM integrated approach in construction project management. overtime wages.

References

Agitiya Wahyu, A., Gunasti, A., & Cahya Dewi, I. (2024). Standarisasi Kinerja Waktu Dan Biaya Dengan Metode Earned Value Pada Tahap Pekerjaan Struktur Proyek. Sustainable Civil Building Management And Engineering Journal, 1(1), 40. Https://Doi.Org/10.47134/Scbmej.V1i1.2138

Farina, T., Nugraha, S., Mulyawan, A., & Wijaya, A. (2024). Pengakuan Dan Perlindungan Hutan Adat Dalam Mewujudkan Hak Masyarakat Hukum Adat Di Provinsi Kalimantan Tengah. Unes Law Review, 6(3), 9377–9389. Retrieved From Https://Review-Unes.Com/Https://Creativecommons.Org/Licenses/By/4.0/

Hakim, I., Asdi, & Afriliansyah, T. (2024). Implementasi Algoritma Komputasi Linear Regression Untuk Optimasi Prediksi Hasil Pertanian. Jurnal Penerapan Sistem Informasi (Komputer & Manajemen), 5(3), 1423–1434.

Ikhtisholiyah, Wardana, M. H. I., & Agustiar, I. (2023). PENERAPAN METODE CPM DAN TIME-COST TRADE-OFF DALAM MENGELOLA WAKTU SERTA BIAYA PROYEK KONSTRUKSI X. Jurnal Ilmiah Teknik Sipil, 12(2), 19–33.

Kusumadarma, I. A., Pratami, D., Yasa, I. P., & Tripiawan, W. (2020). Developing Project Schedule In Telecommunication Projects Using Critical Path Method (CPM). International Journal Of Integrated Engineering, 12(3), 60–67. Https://Doi.Org/10.30880/Ijie.2020.12.03.008

Nardiansyah, A., & Intansari, D. W. A. (2022). Optimasi Waktu Dan Biaya Dengan Metode Crashing Pada Proyek Pembangunan Jalan Simp. 4 Kaliorang – Talisayan Kalimantan Timur. Jurnal Kridatama Sains Dan Teknologi, 4(02), 127–141. Https://Doi.Org/10.53863/Kst.V4i02.498

Nuraeni, S. R., & Adman. (2017). Pengaruh Kolaborasi Dengan Pemasok Terhadap Efisiensi Pengadaan Logistik. Jurnal Logistica, 53(9), 8–24.

Rima, & Naim. (2025). Infrastruktur Berkelanjutan : Analisis Bantuan Luar Negeri Jepang Dalam Mendorong Pertumbuhan Ekonomi Indonesia. Jurnal Akutansi, Manajemen, Dan Ilmu Pendidikan (JAMED), 1(1), 19–33.

Rottie, F. V. A., Runtu, F. I., Umboh, A. H., & Bumbungan, S. J. (2024). Studi Penggunaan Metode Time Cost Trade Off Untuk Percepatan Waktu Pada Proyek Pembangunan Jembatan Dan Oprit Boulevard II. Jurnal SAINTEK, 04(01), 1–6.

Zakaria Umar, M. (2022). Dampak Pandemi Covid-19 Terhadap Pendapatan Para Pengusaha Bahan Bangunan Lokal Di Kota Kendari. Jurnal Arsitektur Zonasi, 5(21), 2022. Retrieved From Http://Ejournal.Upi.Edu/Index.Php/Jaz-

Zhang, P. (2024). Construction Of Virtual Simulation Experiment Platform For Intelligent Construction Based On Statistical Machine Learning System Modelling. Transactions Of The Royal Institution Of Naval Architects Part A: International Journal Of Maritime Engineering, 1(1), A545–A555. Https://Doi.Org/10.5750/Ijme.V1i1.1384

Downloads

Published

2025-04-10

How to Cite

Mahendra, M. O., Saputro, T. E., & Putra, A. F. S. (2025). Analisis Optimalisasi Waktu dan Biaya dengan Penambahan Jam Metode Time Cost Trade Off. Jurnal Teknik Industri Terintegrasi (JUTIN), 8(2), 1900–1907. https://doi.org/10.31004/jutin.v8i2.44078

Issue

Section

Articles of Research

Similar Articles

<< < 5 6 7 8 9 10 11 12 13 14 > >> 

You may also start an advanced similarity search for this article.