Penerapan Metode Lean Six Sigma (DMAIC) untuk Meningkatkan Produktivitas Plat Silinder di PT. X
DOI:
https://doi.org/10.31004/jutin.v8i3.47306Keywords:
Calculation Of OEE Value, Lean Six Sigma, DMAIC, ProductivityAbstract
PT. X is a manufacturing company that produces fire extinguishers (APAR), where cylindrical plate welding is a critical process. However, the process is often inefficient due to several non-value-added steps. This study aims to improve welding productivity using Lean Six Sigma through the DMAIC (Define, Measure, Analyze, Improve, Control) approach and by measuring Overall Equipment Effectiveness (OEE). The initial OEE value was 67.49%, far below the world-class standard of 85%. Pareto analysis showed the highest downtime was due to cycle time issues, especially during setup and cutting of additional plates. Improvements were made by eliminating the cutting process and adding a stopper to ensure accurate welding positions. These changes reduced the cycle time from 180 seconds to 120 seconds and increased the OEE to 76.12%.References
Alhadihaq, M. Y., & Sumiati, N. (2023). 4057-Article Text-21708-1-10-20240113. 10(2), 863–870.
Ashari, D. D., Naubnome, V., & Fauji, N. (2022). Analisis Kinerja Mesin Amg Cnc Plate Cutting Menggunakan Metode Oee (Overall Equipment Effectiveness). Rotor, 15(2), 37. https://doi.org/10.19184/rotor.v15i2.32408
Fatkhurrohman, A., & Subawa. (2016). Penerapan Kaizen dalam Meningkatkan Efisiensi dan Kualitas Produk pada Bagian Banbury PT. Bridgestone Tire Indonesia. Jurnal Administrasi Kantor, 4(1), 14–31.
Pratama, H., Sutaarga, O., & Rohman, Z. (2020). Analisis Produktivitas Mesin Body Hydraulic One Stroke 30T Dengan Metode Overall Equipment Effectiveness (Oee) Di Pt. Sel-Sem Tbk., Tangerang. Journal Industrial Manufacturing, 5(1), 83. https://doi.org/10.31000/jim.v5i1.2441
Ramadhani, I., Rasyid, A., & Junus, S. (2023). Identifikasi Dan Minimasi Waste Produksi Keripik Pisang Keju Menggunakan Metode Lean Manufacturing. RADIAL : Jurnal Peradaban Sains, Rekayasa Dan Teknologi, 11(2), 240–250. https://doi.org/10.37971/radial.v11i2.398
Rollandiaz, S., & Iskandar, Y. A. (2024). Evaluasi Keterlambatan Pengiriman Produk Bahan Bakar Minyak Menggunakan Lean Six Sigma. INFOTECH Journal, 10(1), 74–83. https://doi.org/10.31949/infotech.v10i1.8796
Saefullah, A., Fadli, A., Nuryahati, Agustina, I., & Abas, F. (2023). Implementasi Prinsip Pareto Dan Penentuan Biaya Usaha Seblak Naha Rindu. Jurnal Media Wahana Ekonomika, 20(1), 1–13. https://doi.org/10.31851/jmwe.v20i1.11077
Sumasto, F., Satria, P., & Rusmiati, E. (2022). Implementasi Pendekatan DMAIC untuk Quality Improvement pada Industri Manufaktur Kereta Api. Jurnal INTECH Teknik Industri Universitas Serang Raya, 8(2), 161–170. https://doi.org/10.30656/intech.v8i2.4734
Supriyati, S., & Hasbullah, H. (2020). Analisis cacat painting komponen automotive dengan pendekatan DMAIC-FMEA. Operations Excellence: Journal of Applied Industrial Engineering, 12(1), 104. https://doi.org/10.22441/oe.2020.v12.i1.009
Tri, S., & Wiyatno, N. (2024). Jurnal Informasi dan Teknologi Mesin dengan Pendekatan Lean Manufacturing. 3–10. https://doi.org/10.60083/jidt.v6i2.584
Wijaya, T., Wiramijaya, F., Rahmania, A., & Oktaviani, S. (2021). Penerapan Metode Lean Six Sigma Dalam Upaya Rekrutmen Peserta PPU Badan Usaha: Study Kasus Proses Telemarketing Kantor Cabang Jakarta Selatan. Jurnal Jaminan Kesehatan Nasional, 1(1), 67–80. https://doi.org/10.53756/jjkn.v1i1.19
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Fadyla Indra Kusuma, Hafidz Akbar Halim, Ade Nurul Hidayat

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.