Kajian manajemen risiko pada pembangunan gedung kantor PKK, Dekranasda dan UMKM Center Kota Makassar
DOI:
https://doi.org/10.31004/jutin.v8i1.40955Keywords:
Risk of Delay, SPSS 25, Logistic Regression AnalysisAbstract
The implementation of a construction project anywhere and in any form will never be free from risks, whether small-scale or large-scale risks. The smaller the potential risk, the more profitable the project will be, both in terms of costs and construction implementation. The larger the scale of a project, the greater the potential risks that arise which, if not handled properly, will hamper project implementation. One of the projects that was used as the object of study was the Implementation of the PKK, Dekranasda and UMKM Center Office Building Project for Makassar City. This project has a risk of delays so risk management analysis will be carried out with a formulation to obtain mitigation that suits the needs of the workplace. Data collection was carried out by identifying factors from previous research, a preliminary survey was carried out to determine factors that were relevant to the project conditions. After the relevant factors are distributed, a questionnaire is distributed to obtain data on the object's perception of the factors in the questionnaire. So the collected data is processed and analyzed using the SPSS 25 application using logistic regression analysis. The results of research using logistic regression analysis show is one main factor that influences the risk of delays in project work, namely schedule preparation. If the schedule preparation factors are carried out poorly then the chance of delays is 74.95%.References
Akbar, Y. R., & Priyanto, B. (2023). Analisis Manajemen Risiko Pada Proyek Pembangunan Access Road Bandara Internasional Dhoho Kediri. Journal of Comprehensive Science (JCS), 2(7), 2097-2103.
Alamsyah, C. W., Walujodjati, E., & Rahadian, S. P. (2021). Analisis manajemen risiko K3 pekerjaan jalan tol Cisumdawu phase III. Jurnal Konstruksi, 19(1), 60-69.
Apriliyani, M. A. (2020). Analisa Keterlambatan Berbasis Manajemen Risiko Pada Proyek Warehouse Lazada Tahap 2. Rekayasa Sipil, 8(2), 326487.
Arti, S. S., & Juan, J. D. G. (2023). Analisis Manajemen Risiko Terhadap Keterlambatan Waktu Pekerjaan Pada Proyek Pembangunan Wiego Warehouse. Prosiding Konferensi Nasional Social & Engineering Polmed (KONSEP), 4(1), 893-904.
Astiti, N. P. M., Norken, N., & Purbawijaya, I. B. N. (2015). Analisis Risiko Pelaksanaan Pembangunan Jalan Tol Benoa-Bandara-Nusa Dua. Jurnal Spektran, 3 (2).
Darma, Y., & Ashad, H. (2022). Kajian Manajemen Risiko Pada Pembangunan Gedung Islamic Center Tahap III Kabupaten Bone. Jurnal Konstruksi: Teknik, Infrastruktur dan Sains, 1(11), 37-48.
Dewi, A. A. D. P., Sudarsana, I. D. K., & Jayantika, P. Y. (2023). Manajemen Risiko Pada Pembangunan Pengembangan Rumah Sakit Umum Tabanan Yang Sedang Beroperasi (Studi Kasus Pada Pembangunan Gedung Nicu–Ponek BRSU Tabanan Bali). Jurnal Teknik Sipil Terapan, 5(1), 41-53.
Fahlevi, A. E., Safaria, F., & Susetyaningsih, A. (2019). Analisis Manajemen Risiko Pelaksanaan Proyek Konstruksi (Studi Kasus Thee Matic Mall dan Hotel Majalaya Kabupaten Bandung). Jurnal Konstruksi, 17(1), 28-36.
Fauzi, R. R., Johari, G. J., Hantari, A. N., & Triguna, M. I. (2022). Identifikasi dan Penilaian Risiko pada Proyek Pembangunan Stasiun Garut Cibatu. Jurnal Konstruksi, 20(1), 51-61.
Fazis, M., & Tugiah, T. (2022). Perencanaan Proyek dan Penjadwalan Proyek. Jurnal Sosial Teknologi, 2(12), 1365-1377.
Firmansyah, Y., Natasaputra, S., & Tua, P. R. (2023). Analisis Resiko Keterlambatan Pelaksanaan Proyek Pemetaan Integrasi Neraca Spasial Diwilayah Sungai Ciliwung Cisadane. Jurnal Teknik| Majalah Ilmiah Fakultas Teknik UNPAK, 24(1).
Harjono, D., & Hakim, E. A. (2021). Analisis Manajemen Risiko Pelaksanaan Pembangunan Gedung E Rsud Ra Basoeni Kabupaten Mojokerto. Program Studi Persatuan Insinyur Indonesia, 1(1).
Kusumadewi, A., Listiana, V., Hatmoko, J. U. D., & Hermawan, F. (2017). Analisa manajemen risiko tahap konstruksi pada proyek kereta cepat Jakarta-Bandung. Jurnal Karya Teknik Sipil, 6(1), 157-164.
Lamunuhia, S. F. (2018). Pengaruh Audit Tenure, Rotasi Kap, Ukuran Perusahaan Klien Dan Spesialisasi Auditor Terhadap Kualitas Audit (Studi pada Perusahaan Perbankan yang Terdapat di BEI 2014-2016).
Nugroho, A. W., Tukiyo, T., & Fithra, H. (2022). Identification of Factors Caused The Risk of Time Delays in The Pulogadung. International Journal of Engineering, Science and Information Technology, 2(2), 41-52.
Nurlela, N., & Suprapto, H. (2014). Identifikasi dan analisis manajemen risiko pada proyek pembangunan infrastruktur bangunan gedung bertingkat. Jurnal Ilmiah Desain & Konstruksi, 13(2).
Pagehgiri, J., Putra, I. K. A. A., & Dwipayana, I. W. M. (2021). Identifikasi Penilaian Dan Mitigasi Risiko Pada Proyek Villa Nini Elly. Jurnal Teknik Gradien, 13(1), 61-73.
Pondaag, N. E., Malingkas, G. Y., & Mangare, J. B. (2020). Analisis Penyebab Keterlambatan Waktu Pelaksanaan Proyek Pada Perumahan Grand Victorian Kairagi. Jurnal Sipil Statik, 8(4).
Revantoro, N. B., & Djatmiko, B. Analisis Risiko Dalam Proyek Jalan Raya Di Kabupaten Malang.
Ronny, A. Implementasi Manajemen Risiko Proyek Pada Pt. Xx Dengan Menggunakan Pendekatan House Of Risk (HOR) Berdasarkan ISO 31000: 2018. Jurnal Teknik Industri Universitas Tanjungpura, 4(2).
Sanaky, M. M. (2021). Analisis Faktor-Faktor Keterlambatan Pada Proyek Pembangunan Gedung Asrama Man 1 Tulehu Maluku Tengah. Jurnal Simetrik, 11(1), 432-439.
Sandyavitri, A. (2009). Manajemen Resiko di Proyek Konstruksi. Media Komunikasi Teknik Sipil, 17(1), 23-38.
Sembiring, P. (2023). Analisis Regresi Logistik Untuk Menentukan Faktor-Faktor Yang Mempengaruhi Kesejahteraan Masyarakat Kabupaten/Kota Di Pulau Nias. FARABI: Jurnal Matematika dan Pendidikan Matematika, 6(1), 25-31.
Setiawan, M. A., Sucita, I. K., & Sarwono, B. (2021). Penerapan Manajemen Risiko Pada Proyek Konstruksi Gedung (Studi Kasus Proyek Apartemen Apple 3 Condovilla–Jakarta Selatan). Construction and Material Journal, 3(3), 197-205.
Simanjuntak, I. J., Siagian, R. T., Prasetyo, R., Rozak, N. F., & Purba, H. H. (2022). Manajemen Risiko Pada Proyek Konstruksi Jembatan: Kajian Literatur Sistematis. Jurnal Teknologi dan Manajemen, 20(1), 59-76.
Tampil, Y., Komaliq, H., & Langi, Y. (2017). Analisis Regresi Logistik Untuk Menentukan Faktor-Faktor Yang Mempengaruhi Indeks Prestasi Kumulatif (IPK) Mahasiswa FMIPA Universitas Sam Ratulangi Manado. d'CARTESIAN: Jurnal Matematika dan Aplikasi, 6(2), 56-62.
Varamita, A. (2017). Analisis regresi logistik dan aplikasinya pada penyakit anemia untuk ibu hamil di RSKD Ibu dan Anak Siti Fatimah Makassar (Doctoral dissertation, FMIPA).
Vheatrieze, A. B. V. A. B. (2021). Tinjauan Manajemen Risiko Pra Konstruksi, Pelaksanaan Konstruksi, dan Pasca Konstruksi Pada Proyek Pembangunan Gedung Student Center Politeknik Negeri Indramayu. Prosiding FTSP Series.
Wally, S. N., Jamlaay, O., & Marantika, M. (2022). Analisis Manajemen Risiko Pada Proyek Pembangunan Gedung Laboratorium Terpadu Dan Perpustakaan Man 1 Maluku Tengah. Menara: Jurnal Teknik Sipil, 17(2), 61-69.
Wilantara, B., Hasan, A., & Jumas, D. Y. (2025). Faktor-Faktor Yang Mempengaruhi Kualitas Subkontraktor Terhadap Kinerja Main Kontraktor Pada Pekerjaan Jalan Provinsi Bengkulu. Jurnal Teknik Sipil Institut Teknologi Padang, 12(1), 43-052.
Akbar, Y. R., & Priyanto, B. (2023). Analisis Manajemen Risiko Pada Proyek Pembangunan Access Road Bandara Internasional Dhoho Kediri. Journal of Comprehensive Science (JCS), 2(7), 2097-2103.
Alamsyah, C. W., Walujodjati, E., & Rahadian, S. P. (2021). Analisis manajemen risiko K3 pekerjaan jalan tol Cisumdawu phase III. Jurnal Konstruksi, 19(1), 60-69.
Apriliyani, M. A. (2020). Analisa Keterlambatan Berbasis Manajemen Risiko Pada Proyek Warehouse Lazada Tahap 2. Rekayasa Sipil, 8(2), 326487.
Arti, S. S., & Juan, J. D. G. (2023). Analisis Manajemen Risiko Terhadap Keterlambatan Waktu Pekerjaan Pada Proyek Pembangunan Wiego Warehouse. Prosiding Konferensi Nasional Social & Engineering Polmed (KONSEP), 4(1), 893-904.
Astiti, N. P. M., Norken, N., & Purbawijaya, I. B. N. (2015). Analisis Risiko Pelaksanaan Pembangunan Jalan Tol Benoa-Bandara-Nusa Dua. Jurnal Spektran, 3 (2).
Darma, Y., & Ashad, H. (2022). Kajian Manajemen Risiko Pada Pembangunan Gedung Islamic Center Tahap III Kabupaten Bone. Jurnal Konstruksi: Teknik, Infrastruktur dan Sains, 1(11), 37-48.
Dewi, A. A. D. P., Sudarsana, I. D. K., & Jayantika, P. Y. (2023). Manajemen Risiko Pada Pembangunan Pengembangan Rumah Sakit Umum Tabanan Yang Sedang Beroperasi (Studi Kasus Pada Pembangunan Gedung Nicu–Ponek BRSU Tabanan Bali). Jurnal Teknik Sipil Terapan, 5(1), 41-53.
Fahlevi, A. E., Safaria, F., & Susetyaningsih, A. (2019). Analisis Manajemen Risiko Pelaksanaan Proyek Konstruksi (Studi Kasus Thee Matic Mall dan Hotel Majalaya Kabupaten Bandung). Jurnal Konstruksi, 17(1), 28-36.
Fauzi, R. R., Johari, G. J., Hantari, A. N., & Triguna, M. I. (2022). Identifikasi dan Penilaian Risiko pada Proyek Pembangunan Stasiun Garut Cibatu. Jurnal Konstruksi, 20(1), 51-61.
Fazis, M., & Tugiah, T. (2022). Perencanaan Proyek dan Penjadwalan Proyek. Jurnal Sosial Teknologi, 2(12), 1365-1377.
Firmansyah, Y., Natasaputra, S., & Tua, P. R. (2023). Analisis Resiko Keterlambatan Pelaksanaan Proyek Pemetaan Integrasi Neraca Spasial Diwilayah Sungai Ciliwung Cisadane. Jurnal Teknik| Majalah Ilmiah Fakultas Teknik UNPAK, 24(1).
Harjono, D., & Hakim, E. A. (2021). Analisis Manajemen Risiko Pelaksanaan Pembangunan Gedung E Rsud Ra Basoeni Kabupaten Mojokerto. Program Studi Persatuan Insinyur Indonesia, 1(1).
Kusumadewi, A., Listiana, V., Hatmoko, J. U. D., & Hermawan, F. (2017). Analisa manajemen risiko tahap konstruksi pada proyek kereta cepat Jakarta-Bandung. Jurnal Karya Teknik Sipil, 6(1), 157-164.
Lamunuhia, S. F. (2018). Pengaruh Audit Tenure, Rotasi Kap, Ukuran Perusahaan Klien Dan Spesialisasi Auditor Terhadap Kualitas Audit (Studi pada Perusahaan Perbankan yang Terdapat di BEI 2014-2016).
Nugroho, A. W., Tukiyo, T., & Fithra, H. (2022). Identification of Factors Caused The Risk of Time Delays in The Pulogadung. International Journal of Engineering, Science and Information Technology, 2(2), 41-52.
Nurlela, N., & Suprapto, H. (2014). Identifikasi dan analisis manajemen risiko pada proyek pembangunan infrastruktur bangunan gedung bertingkat. Jurnal Ilmiah Desain & Konstruksi, 13(2).
Pagehgiri, J., Putra, I. K. A. A., & Dwipayana, I. W. M. (2021). Identifikasi Penilaian Dan Mitigasi Risiko Pada Proyek Villa Nini Elly. Jurnal Teknik Gradien, 13(1), 61-73.
Pondaag, N. E., Malingkas, G. Y., & Mangare, J. B. (2020). Analisis Penyebab Keterlambatan Waktu Pelaksanaan Proyek Pada Perumahan Grand Victorian Kairagi. Jurnal Sipil Statik, 8(4).
Revantoro, N. B., & Djatmiko, B. Analisis Risiko Dalam Proyek Jalan Raya Di Kabupaten Malang.
Ronny, A. Implementasi Manajemen Risiko Proyek Pada Pt. Xx Dengan Menggunakan Pendekatan House Of Risk (HOR) Berdasarkan ISO 31000: 2018. Jurnal Teknik Industri Universitas Tanjungpura, 4(2).
Sanaky, M. M. (2021). Analisis Faktor-Faktor Keterlambatan Pada Proyek Pembangunan Gedung Asrama Man 1 Tulehu Maluku Tengah. Jurnal Simetrik, 11(1), 432-439.
Sandyavitri, A. (2009). Manajemen Resiko di Proyek Konstruksi. Media Komunikasi Teknik Sipil, 17(1), 23-38.
Sembiring, P. (2023). Analisis Regresi Logistik Untuk Menentukan Faktor-Faktor Yang Mempengaruhi Kesejahteraan Masyarakat Kabupaten/Kota Di Pulau Nias. FARABI: Jurnal Matematika dan Pendidikan Matematika, 6(1), 25-31.
Setiawan, M. A., Sucita, I. K., & Sarwono, B. (2021). Penerapan Manajemen Risiko Pada Proyek Konstruksi Gedung (Studi Kasus Proyek Apartemen Apple 3 Condovilla–Jakarta Selatan). Construction and Material Journal, 3(3), 197-205.
Simanjuntak, I. J., Siagian, R. T., Prasetyo, R., Rozak, N. F., & Purba, H. H. (2022). Manajemen Risiko Pada Proyek Konstruksi Jembatan: Kajian Literatur Sistematis. Jurnal Teknologi dan Manajemen, 20(1), 59-76.
Tampil, Y., Komaliq, H., & Langi, Y. (2017). Analisis Regresi Logistik Untuk Menentukan Faktor-Faktor Yang Mempengaruhi Indeks Prestasi Kumulatif (IPK) Mahasiswa FMIPA Universitas Sam Ratulangi Manado. d'CARTESIAN: Jurnal Matematika dan Aplikasi, 6(2), 56-62.
Varamita, A. (2017). Analisis regresi logistik dan aplikasinya pada penyakit anemia untuk ibu hamil di RSKD Ibu dan Anak Siti Fatimah Makassar (Doctoral dissertation, FMIPA).
Vheatrieze, A. B. V. A. B. (2021). Tinjauan Manajemen Risiko Pra Konstruksi, Pelaksanaan Konstruksi, dan Pasca Konstruksi Pada Proyek Pembangunan Gedung Student Center Politeknik Negeri Indramayu. Prosiding FTSP Series.
Wally, S. N., Jamlaay, O., & Marantika, M. (2022). Analisis Manajemen Risiko Pada Proyek Pembangunan Gedung Laboratorium Terpadu Dan Perpustakaan Man 1 Maluku Tengah. Menara: Jurnal Teknik Sipil, 17(2), 61-69.
Wilantara, B., Hasan, A., & Jumas, D. Y. (2025). Faktor-Faktor Yang Mempengaruhi Kualitas Subkontraktor Terhadap Kinerja Main Kontraktor Pada Pekerjaan Jalan Provinsi Bengkulu. Jurnal Teknik Sipil Institut Teknologi Padang, 12(1), 43-052.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Mohammad Tharieq Sany, Hanafi Ashad, Muhammad Husni Maricar

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.