Optimasi penggunaan dan perawatan pada mesin unit Phonska IV untuk meningkatkan produksi pupuk pada PT. XYZ

Authors

  • Endang Agustina Universitas Pembangunan Nasional Veteran Jawa Timur
  • Rizqi Novita Sari Universitas Pembangunan Nasional Veteran Jawa Timur

DOI:

https://doi.org/10.31004/jutin.v8i1.39641

Keywords:

Downtime, Components, Optimal, Company, Software

Abstract

PT XYZ is a company engaged in the production of fertilizers. With the monthly targets that must be met. The phonka IV unit has several categories of machines such as the Rotating category, the Instrument category, the Electrical category, each category has several problems with its components. So that it can reduce the production that must be achieved and financial losses due to Downtime. Therefore, Company XYZ must calculate to find out the most optimal time interval to reduce damage to each category of its machines. The method used to solve this problem is to use the FMEA and RCM methods with the help of excel and minitab software to facilitate data calculations. The results of data processing show that the total RPN obtained with a total of 470. After calculating the Company's interval. The Rotation category should be done every 31.61 hours, for the Instrument category it should be done every 2.81 hours, for the Electrical category it should be done every 2.83 hours. Then the Company can find out the planned schedule.

References

Akbar1, M. R., & Wiwin Widiasih2. (2022). Analisis Perawatan Mesin Bubut Dengan Metode Preventive Maintenance Guna Menghindari Kerusakan Secara Mendadak Dan Untuk Menghitung Biaya Perawatan. Jurnal Senopati, 1 No 2, 32–45.

Daniel Chrisnanda. (2024). Analisis Manajemen Perawatan Mesin Produksi Kemasan Plastik Spout Dengan Metode Reliability Centered Maintenance (Rcm). Jurnal Penelitian Rumpun Ilmu Teknik, 3(3), 117–128. Https://Doi.Org/10.55606/Juprit.V3i3.4236

Hidayat, A. R. (2023). Analisa Waktu Optimasi Perawatan Mesin Cnc Milling Dengan Pendekatan Value Stream Mapping Serta Perbaikan Dengan Failur Mode And Effect Analysis Pada Mesin Cnc Milling. Jurnal Rekayasa Mesin, 18(3), 345. Https://Doi.Org/10.32497/Jrm.V18i3.4099

Ihsan, A. S., Jufriyanto, M., & Rizqi, A. W. (2024). Pengendalian Kualitas Produk Pupuk Phonska Dengan Metode Six Sigma Dan Failure Mode Analysis. G-Tech: Jurnal Teknologi Terapan, 8(2), 921–932. Https://Doi.Org/10.33379/Gtech.V8i2.4085

Rodiah. (2020). Implementasi High Availability Untuk Pengurangan Waktu Downtime Pada Jaringan Dengan Protokol High Availability First Hop Redudancy Protocol (Fhrp). Jurnal Ilmiah Informatika Komputer, 25(2), 147–159. Https://Doi.Org/10.35760/Ik.2020.V25i2.2982

Samharil, F., Ismiyah, E., & Dhartikasari Priyana, E. (2022). Perancangan Pemeliharaan Mesin Filter Press Dengan Metode Fmeca Dan Reliability Centered Maintenance (Rcm) (Studi Kasus Pt. Xyz). Jurnal Teknik Industri: Jurnal Hasil Penelitian Dan Karya Ilmiah Dalam Bidang Teknik Industri, 8(2), 335. Https://Doi.Org/10.24014/Jti.V8i2.20094

Saputra, Y., Widyantoro, M., & Rosihan, R. I. (2024). Perencanaan Perawatan Mesin Dengan Metode Reliability Centered Maintenance Dan Age Replacement. Jurnal Mekanova?: Mekanikal, Inovasi Dan Teknologi, Vol 10 N(P-Issn?: 2477-5029 E-Issn?: 2502-0498ij).

Subekti, J., Wibowo, W., Ningrum Astriawati, & Muhammad Hamzah Fadholy. (2022). Optimalisasi Perawatan Sistem Pendingin Mesin Utama Tipe Hansin Glu28ag Pada Kapal. Dinamika Bahari, 3(1), 60–68. Https://Doi.Org/10.46484/Db.V3i1.303

Downloads

Published

2025-01-13

How to Cite

Agustina, E., & Sari, R. N. (2025). Optimasi penggunaan dan perawatan pada mesin unit Phonska IV untuk meningkatkan produksi pupuk pada PT. XYZ. Jurnal Teknik Industri Terintegrasi (JUTIN), 8(1), 318–329. https://doi.org/10.31004/jutin.v8i1.39641

Issue

Section

Articles of Research

Similar Articles

1 2 3 4 5 6 7 > >> 

You may also start an advanced similarity search for this article.