Analisis Kinerja Waktu dan Biaya Proyek Renovasi Kolam Renang Ranca Tales Mini Waterboom Menggunakan Metode Earned Value Management

Authors

  • Toto Sudianto Universitas Serang Raya
  • Mohammad Alam Adeyaka Putra Teknik Industri, Universitas Serang Raya
  • Muhammad Akmal Fahrezi Universitas Serang Raya
  • Muhammad Raihan Universitas Serang Raya

DOI:

https://doi.org/10.31004/jutin.v9i1.55063

Keywords:

Earned Value Concept, Project Control, Swimming pool, Renovation

Abstract

This study focuses on the evaluation of costs and time in the renovation project of Ranca Tales Mini Waterboom Swimming Pool by utilizing the Earned Value Management (EVM) method. The data analyzed include the planned budget, implementation schedule, work progress, and actual costs of five main components, namely pool ceramic repair, pool area painting, slide repair, pump and filter repair, and changing room repair. The analysis was carried out by measuring the BCWS, BCWP, and ACWP indicators, as well as variances and project performance indices including SV, CV, SPI, and CPI. The findings of this study show an SPI value of 0.874 which indicates a delay in the project and a CPI value of 0.945 which indicates low cost efficiency. The EVM method has proven successful in providing a quantitative overview of project performance and can be applied as a basis for managerial control and decision making.

References

Afrilia, V., Zulaihati, S., & Kismayanti Respati, D. (2025). Ekopedia : Jurnal Ilmiah Ekonomi. Jurnal Ilmiah Ekonomi, 1(2), 450–458.

Gusti Ayu Putu Candra Dharmayanti, Dewa Ketut Sudarsana, & Ida Ayu Savitri Manohari. (2025). Penerapan Earned Value Concept Pada Proyek Pembangunan Gedung Kuliah Fakultas Kedokteran Universitas Pendidikan Ganesha. Konferensi Nasional Teknik Sipil (Konteks), 2(2). Https://Doi.Org/10.62603/Konteks.V2i2.210

Hasanul Arifin Purba, Surbakti, R., Muhammad Mabrur, & Al Qadry. (2024). Peningkatan Kualitas Fasilitas Toilet Untuk Peningkatan Pelayanan Musholla Babul Jannah Desa Sukamaju Kabupaten Deliserdang. Jurnal Pengabdian Dan Pemberdayaan Masyarakat, 2(2), 94–100. Https://Doi.Org/10.51510/Komposit.V2i2.1922

Jagakarsa, U. T., Jakarta, K., Sianturi, G., Ranap, P., & Naibaho, T. (2025). Kata Kunci: 21(1).

Kartika, W., Buddewi Sukindrawati, & Diki Rohman. (2024). Penerapan Kinerja Proyek Konstruksi Pada Pembangunan Ruas Jalan Dan Jembatan Tawang Ngalang Segmen Iv Menggunakan Earned Value Concept. Agregat, 9(1), 1000–1005. Https://Doi.Org/10.30651/Ag.V9i1.22098

Muhammad Fu’at Chasan, Diah Ayu Septi Fauji, & Hery Purnomo. (2022). Simposium Manajemen Dan Bisnis I Prodi Manajemen Feb Unp Kediri Tahun 2022 Evaluasi Penjadwalan Waktu Dan Biaya Dengan Metode Cpm Dan Gantt Chart Pada Proyek Pembangunan Rumah Tipe 60/72 Griya Keraton Sambirejo Kediri. 4, 1–9.

Pamungkas, A. (2022). Analisis Biaya Dan Waktu Proyek Dalam Proses Kinerja Dengan Menggunakan Metode Earned Value Studi Kasus: Proyek Rancang Bangun Rumah Susun Stasiun Pondok Cina. Jurnal Artesis, 1(2), 187–192.

Papua, M., Dewita, H., & Sembiring, K. (2023). Analisis Penjadwalan Dengan Menggunakan Time Schedule Kurva S Pada Proyek Pembangunan Kantor Cabang Bri Otista Jakarta Timur. Jurnal Teknika, 15(1), 9–22. Https://Doi.Org/10.30736/Jt.V15i1.916

Pdg, C., & Berthon, J. (2024). Greentech Greentech. Greentech, 1(2), 158–172.

Proyek, M. B., Manangement, E. V., Management, E. V., Literatur, S., Studi, H., Pembayaran, S., Kerja, K., & Proyek, M. (2024). How To Cite: E-Issn: Hutomo, J. O. (2024). Evaluasi Manajemen Proyek Dalam Proses Pengendalian Kinerja Biaya Dan Waktu Studi Kasus Renovasi Asrama Mahasiswa Tangerang. 9(12).

Putra, M. A. A., Fahrezi, M. A., & Sudianto, T. (2025). Studi Cost Benefit Analysis Di Kolam Renang Ranca Tales Mini Waterboom. Jurnal Teknik Industri Terintegrasi, 8(3), 3061–3066. Https://Doi.Org/10.31004/Jutin.V8i3.47681

Rusnani, Enita, Tukidi, & Haryanto, E. (2025). Journal Of Scientech Research And Development. Journal Of Scientech Research And Development, 3(1), 24–32. Https://Idm.Or.Id/Jscr/Index.Php/Jscr/Article/View/14

Salasa, B. S., Away, I. F., & Wardono, H. (2024). Perbandingan Rencana Anggaran Pelaksanaan Dengan Rencana Anggaran Biaya Serta Waktu Pelaksanaan Pada Pekerjaan Peningkatan Struktur Jalan Rasau-Sepulau (Studi Kasus : Jalan Rasau-Sepulau Kalimantan Barat). Jurnal Inersia, 14(2), 9–14. Https://Doi.Org/10.46964/Inersia.V14i2.1032

Sentana, H. S., Suksmono, A. K., & Sari, C. A. N. (2024). Evaluasi Waktu Dan Biaya Menggunakan Earned Value Method (Evm) Pada Gedung Mal Pelayanan Publik (Mpp) Kota Tegal. Pasak: Jurnal Teknik Sipil Dan Bangunan, 2(1), 13–19. Https://Doi.Org/10.32699/Pasak.V2i1.7886

Sumanang, I. R., & Rivai, I. (2021). Evaluasi Biaya Dan Waktu Dengan Earned Value Pada Proyek Gedung Sportainment Telkom Corporate University Gegerkalong Bandung. Jurnal Teknik Sipil-Arsitektur, 20(2), 106–128. Https://Doi.Org/10.54564/Jtsa.V20i2.90

Wahyuni, E., & Hendrawan, B. (2018). Analisis Kinerja Proyek “Y”Menggunakan Metode Earned Value Management (Studi Kasus Di Pt Asian Sealand Engineering). Journal Of Applied Business Administration, 2(1), 60–78. Https://Doi.Org/10.30871/Jaba.V2i1.784

Yani, J. P., & Sylviana, R. (2022). Akselerasi: Jurnal Ilmiah Teknik Sipil. Jurnal Ilmiah Teknik Sipil, 5(2), 65–71.

Downloads

Published

2026-01-20

How to Cite

Sudianto, T., Putra, M. A. A., Fahrezi, M. A., & Raihan, M. (2026). Analisis Kinerja Waktu dan Biaya Proyek Renovasi Kolam Renang Ranca Tales Mini Waterboom Menggunakan Metode Earned Value Management. Jurnal Teknik Industri Terintegrasi (JUTIN), 9(1), 914–924. https://doi.org/10.31004/jutin.v9i1.55063

Issue

Section

Articles of Research

Similar Articles

<< < 3 4 5 6 7 8 9 10 11 12 > >> 

You may also start an advanced similarity search for this article.