Analisis Faktor Keterlambatan Penyelesaian Proyek Peningkatan Jalan Ruas Ambemali (Studi Kasus Jln. Belalo/Lasolo – Jln. Arisunggu)
DOI:
https://doi.org/10.31004/jutin.v7i3.29943Keywords:
Delay factors, Contractor, Man PowerAbstract
Delays in implementing construction projects can have negative impacts on contractors and owners. Contractors whose construction projects are late will experience losses in terms of time and costs, because the profits expected by the contractor will be reduced, or even no profits at all. Respondent characteristics based on the questionnaire were classified into several categories, work experience, latest education, company category and field of work in the company. Factors causing delays in work on the Ambemali Road Improvement construction project, Jln. Belalo – Jln. Lasolo, Wawotobi District, Konawe Regency, according to the perception of PPK/PPTK, Directors, Consultants and Service Providers (Contractors) of PT Kendari Baruga Pratama, is caused by Labor Factors with indicators of contractor negligence, Equipment Factors with indicators of Equipment Damage, material factors with this being the lack of material available around the work site , financial factors indicating limited contractor funds, managerial factors namely inappropriate implementation methods, design suitability factors indicating design changes and other factors namely material sources far from the work location.References
Darmawi, D., Muttaqin, M., & Rauzana, A. (2020). IDENTIFIKASI FAKTOR–FAKTOR UTAMA PENYEBAB TERJADINYA KETERLAMBATAN WAKTU PENYELESAIAN PADA PEKERJAAN INFRASTRUKTUR GEDUNG DI BANDA ACEH. Jurnal Arsip Rekayasa Sipil Dan Perencanaan, 3(1), 70–79. https://doi.org/10.24815/jarsp.v3i1.16456
Elizabeth Nathalia Pondaag, Malingkas, Y. G., & Mangare, J. B. (2020). ANALISIS PENYEBAB KETERLAMBATAN WAKTU PELAKSANAAN PROYEK PADA PERUMAHAN GRAND VICTORIAN KAIRAGI. Jurnal Sipil Statik, 8(4), 621–626.
Fahira Khairani, & Supriyadi, I. (2021). Analisis Faktor Keterlambatan Pada Pembangunan Proyek X. Journal of Applied Civil Engineering and Infrastructure Technology, 2(2). https://doi.org/10.52158/jaceit.v2i2.248
Intan, S., Sapulette, W., & Soukotto, R. C. (2020). Analisa Keterlambatan Waktu Pelaksanaan Proyek Konstruksi Di Kota Ambon. Jurnal Manumata , 6(1).
Isabela, I., & Johari, G. J. (2023). Analisis Risiko Keterlambatan Proyek Pada Pembangunan Revitalisasi Gedung Pasar Rakyat Leles Garut Tahap III. Jurnal Kendali Teknik Dan Sains, 1(4), 62–74. https://doi.org/10.59581/jktswidyakarya.v1i4.1182
Lestari, I. G. A. A. I., Pradnyadari, N. L. M. A. M., & Dewi, N. P. I. C. (2022). ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI KABUPATEN BADUNG. Widya Teknik, 17(01). https://doi.org/10.32795/widyateknik.v17i01.2968
Messah, Y. A., Penyebab, K., Pelaksanaan, K., Konstruksi, P., Di, G., Kupang, K., & Messah, Y. A. (2013). KAJIAN PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTUKSI GEDUNG DI KOTA KUPANG. In Jurnal Teknik Sipil: Vol. II (Issue 2).
Natalia, M., Partawijaya, Y., & Satwarnirat, ). (2018). ANALISIS CRITICAL SUCCESS FACTORS PROYEK KONSTRUKSI
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2024 Putra Sakti, Junarto Junarto
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.