Analisis Faktor Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi pada CV. X Menggunakan Metode FTA

Authors

  • Dwi Meilana Putra Universitas 17 Agustus 1945 Surabaya
  • Masca Indra Triana Universitas 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.31004/jutin.v7i2.28181

Keywords:

Delay Factor, FTA Method, Project Delay, Probability, Construction Project

Abstract

Delays that are not handled immediately can affect the quality of a company's performance. This research was conducted on a construction project undertaken by CV. X. Where 4 construction projects undertaken by CV. X as of January 2024 experienced delays in completion. For this reason, it is necessary to analyze the factors that cause delays in the project by using the FTA (Fault Tree Analysis) method which aims to find fault trees from various errors that will result in the occurrence of unwanted events. Data collection is done by survey using a questionnaire. The results of the questionnaire were then analyzed using the FTA Method and then determining the combination of these factors with a minimum cut set. Based on the results of the analysis using the FTA Method, there are 6 aspects that are factors causing delays, namely aspects of labor; material / equipment aspects; project implementation management aspects; contract aspects; aspects of work documents; aspects of natural conditions and force majors. With the largest probability value, namely the contract aspect of 0.21; project implementation management aspect of 0.18; material / equipment aspect of 0.15; aspects of natural conditions and force majors of 0.12; aspects of work documents of 0.09; aspects of labor of 0.08.

References

Darmawi, D., Muttaqin, M., & Rauzana, A. (2020). IDENTIFIKASI FAKTOR–FAKTOR UTAMA PENYEBAB TERJADINYA KETERLAMBATAN WAKTU PENYELESAIAN PADA PEKERJAAN INFRASTRUKTUR GEDUNG DI BANDA ACEH. Jurnal Arsip Rekayasa Sipil Dan Perencanaan, 3(1), 70–79. https://doi.org/10.24815/jarsp.v3i1.16456

Elizabeth Nathalia Pondaag, Malingkas, Y. G., & Mangare, J. B. (2020). ANALISIS PENYEBAB KETERLAMBATAN WAKTU PELAKSANAAN PROYEK PADA PERUMAHAN GRAND VICTORIAN KAIRAGI. Jurnal Sipil Statik, 8(4), 621–626.

Fahira Khairani, & Supriyadi, I. (2021). Analisis Faktor Keterlambatan Pada Pembangunan Proyek X. Journal of Applied Civil Engineering and Infrastructure Technology, 2(2). https://doi.org/10.52158/jaceit.v2i2.248

Intan, S., Sapulette, W., & Soukotto, R. C. (2020). Analisa Keterlambatan Waktu Pelaksanaan Proyek Konstruksi Di Kota Ambon. Jurnal Manumata , 6(1).

Isabela, I., & Johari, G. J. (2023). Analisis Risiko Keterlambatan Proyek Pada Pembangunan Revitalisasi Gedung Pasar Rakyat Leles Garut Tahap III. Jurnal Kendali Teknik Dan Sains, 1(4), 62–74. https://doi.org/10.59581/jkts-widyakarya.v1i4.1182

Lestari, I. G. A. A. I., Pradnyadari, N. L. M. A. M., & Dewi, N. P. I. C. (2022). ANALISIS FAKTOR-FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTRUKSI DI KABUPATEN BADUNG. Widya Teknik, 17(01). https://doi.org/10.32795/widyateknik.v17i01.2968

Messah, Y. A., Penyebab, K., Pelaksanaan, K., Konstruksi, P., Di, G., Kupang, K., & Messah, Y. A. (2013). KAJIAN PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK KONSTUKSI GEDUNG DI KOTA KUPANG. In Jurnal Teknik Sipil: Vol. II (Issue 2).

Natalia, M., Partawijaya, Y., & Satwarnirat, ). (2018). ANALISIS CRITICAL SUCCESS FACTORS PROYEK KONSTRUKSI DI KOTA PADANG. In Jurnal Fondasi (Vol. 6, Issue 2).

Puspitasari, Y. I., Mangare, J. B., & Pratasis, P. A. K. (2020). ANALISIS FAKTOR-FAKTOR KETERLAMBATAN PADA PROYEK PERUMAHAN CASA DE VIOLA DAN ALTERNATIF PENYELESAIANNYA. Jurnal Sipil Statik, 8(2), 141–146.

Putra Agritama, R., Huda, M., Setiyo Rini, T., Program Studi Teknik Sipil, M., Teknik, F., Jurusan Teknik Sipil, D., & Wijaya Kusuma Surabaya ABSTRAK, U. (2018). FAKTOR-FAKTOR YANG MEMPENGARUHI KETERLAMBATAN PROYEK KONSTRUKSI DI SURABAYA (Vol. 6, Issue 1).

Riadi, M. (2023, June 25). Fault Tree Analysis (FTA) - Fungsi, Metode, Simbol dan Langkah Pembuatan. Kajian Pustaka.

Sahid, M. N., Setianingsih, I., Solikhin, M., Mulyono, G. S., & Rahman, N. (2019). Analisis Faktor-Faktor Penting Penyebab Masalah Penambahan Biaya Pada Proyek Jalan Kabupaten Klaten. Media Teknik Sipil, 17(2). http://ejournal.umm.ac.id/index.php/jmts/article/view/9745

Sugiyono. (2022). Metode Penelitian Kuantitatif, Kualitatif, dan R&D (2nd ed.). Alfabeta.

Sulaiman, M., Munirwansyah, & Azmeri. (2017). ANALISIS PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK DITINJAU DARI WAKTU PELAKSANAAN DI PROVINSI ACEH. Jurnal Teknik Sipil Universitas Syiah Kuala, 1(2).

Suryandono, R. F. (2018). EVALUATION OF DELAY IN CONSTURCTION PROJECT OF JACKET STRUCTURE “MADURA BD” PT.PAL INDONESIA.

Downloads

Published

2024-04-22

How to Cite

Putra, D. M. ., & Triana, M. I. . (2024). Analisis Faktor Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi pada CV. X Menggunakan Metode FTA . Jurnal Teknik Industri Terintegrasi (JUTIN), 7(2), 969–979. https://doi.org/10.31004/jutin.v7i2.28181

Issue

Section

Articles of Research